[xwiki-devs] New planning for XE 1.4 releases
Hi, Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates: * XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13 Let me know if you have any concern with these dates. Thanks, -- Jean-Vincent Drean
On 2 avr. 08, at 11:20, Jean-Vincent Drean wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd
Tomorrow == April 3rd :) Does this imply that XE1.4M1 == XE1.4M2? Cheers, Fabio
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction : * XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16 -- Jean-Vincent Drean
Jean-Vincent Drean wrote:
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction :
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
+1 -- Sergiu Dumitriu http://purl.org/net/sergiu/
+1 On Wed, Apr 2, 2008 at 11:27 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction :
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
-- Jean-Vincent Drean _______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne
On Apr 2, 2008, at 11:27 AM, Jean-Vincent Drean wrote:
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction :
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
-0 I'd really like that we don't change the final release date and keep it as planned. It's not good practice to shift. We should instead modify slightly the intermediary dates but keep the same final date. Of course this means we'll have a little bit less content but that's not important. What's important is that we 1) release often and 2) keep the dates that we announce. Thanks -Vincent
On Apr 2, 2008, at 11:47 AM, Vincent Massol wrote:
On Apr 2, 2008, at 11:27 AM, Jean-Vincent Drean wrote:
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction :
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
-0
I'd really like that we don't change the final release date and keep it as planned. It's not good practice to shift. We should instead modify slightly the intermediary dates but keep the same final date. Of course this means we'll have a little bit less content but that's not important. What's important is that we 1) release often and 2) keep the dates that we announce.
Before we finalize let's review what we want to include in 1.4M2: 1) new xmlrpc improvements (Fabio) 2) improved stats performance (ThomasM) 3) Skins extensions (Sergiu) 4) some perf improvements (JV) Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks in order to have the same final release date for 1.4. What can be done in 1) through 4) within 2 weeks (10 days) starting today? Thanks -Vincent
On 2 avr. 08, at 13:44, Vincent Massol wrote:
Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks in order to have the same final release date for 1.4. What can be done in 1) through 4) within 2 weeks (10 days) starting today?
XMLRPC is almost done (modulo some issues, look at my previous email). So in 10 days, even less, it will be ready. Cheers, Fabio
On Wed, Apr 2, 2008 at 1:44 PM, Vincent Massol <vincent@massol.net> wrote:
On Apr 2, 2008, at 11:47 AM, Vincent Massol wrote:
On Apr 2, 2008, at 11:27 AM, Jean-Vincent Drean wrote:
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction :
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
-0
I'd really like that we don't change the final release date and keep it as planned. It's not good practice to shift. We should instead modify slightly the intermediary dates but keep the same final date. Of course this means we'll have a little bit less content but that's not important. What's important is that we 1) release often and 2) keep the dates that we announce.
Before we finalize let's review what we want to include in 1.4M2:
1) new xmlrpc improvements (Fabio) 2) improved stats performance (ThomasM) 3) Skins extensions (Sergiu) 4) some perf improvements (JV)
Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks in order to have the same final release date for 1.4. What can be done in 1) through 4) within 2 weeks (10 days) starting today?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
Ok for 2) I think -- Thomas Mortagne
Vincent Massol wrote:
On Apr 2, 2008, at 11:47 AM, Vincent Massol wrote:
On Apr 2, 2008, at 11:27 AM, Jean-Vincent Drean wrote:
On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv@xwiki.com> wrote:
Hi,
Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to modify the planning a bit. So here are the proposed dates:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 3rd * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 8 * XE 1.4 Final - May 13
Oops, correction :
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16 -0
I'd really like that we don't change the final release date and keep it as planned. It's not good practice to shift. We should instead modify slightly the intermediary dates but keep the same final date. Of course this means we'll have a little bit less content but that's not important. What's important is that we 1) release often and 2) keep the dates that we announce.
Before we finalize let's review what we want to include in 1.4M2:
1) new xmlrpc improvements (Fabio) 2) improved stats performance (ThomasM) 3) Skins extensions (Sergiu) 4) some perf improvements (JV)
Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks in order to have the same final release date for 1.4. What can be done in 1) through 4) within 2 weeks (10 days) starting today?
Thanks -Vincent
OK for 3. -- Sergiu Dumitriu http://purl.org/net/sergiu/
On Wed, Apr 2, 2008 at 1:44 PM, Vincent Massol <vincent@massol.net> wrote:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
Before we finalize let's review what we want to include in 1.4M2:
1) new xmlrpc improvements (Fabio) 2) improved stats performance (ThomasM) 3) Skins extensions (Sergiu) 4) some perf improvements (JV)
Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks in order to have the same final release date for 1.4. What can be done in 1) through 4) within 2 weeks (10 days) starting today?
And ok for 4) Since everyone is ok to have a 2 weeks long 1.4M2 let's keep the old release dates : * XE 1.4 M1 - today * XE 1.4 M2 - April 18 * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 2 * XE 1.4 Final - May 6 If it's ok for everyone I'll update those dates in JIRA today. Thanks, -- Jean-Vincent Drean
participants (5)
-
Fabio Mancinelli -
Jean-Vincent Drean -
Sergiu Dumitriu -
Thomas Mortagne -
Vincent Massol