[xwiki-devs] [Proposal] New Release Dates for the 2.0 Release
Hi, Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release. I'm proposing: * 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case) WDYT? Thanks -Vincent
Hi, On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol <vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Sounds good to me. +1 Guillaume
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
-- Guillaume Lerouge Product Manager - XWiki Skype: wikibc Twitter: glerouge http://guillaumelerouge.com/
+1 Thanks, Marius Vincent Massol wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
Vincent Massol wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
Waiting for bug reports in the weekend is not such a great idea. -- Sergiu Dumitriu http://purl.org/net/sergiu/
On Aug 28, 2009, at 12:52 AM, Sergiu Dumitriu wrote:
Vincent Massol wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
Waiting for bug reports in the weekend is not such a great idea.
Why do you say this? I just used our rule or releasing on Mondays and that also allows us some time on we in case we have something urgent to fix at the last moment. What do you propose? Thanks -Vincent
Guys, Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable: * XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep Here's my +1 Thanks -Vincent On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
+1, JV. On Thu, Sep 3, 2009 at 11:25 AM, Vincent Massol <vincent@massol.net> wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
Thanks -Vincent
On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
+1 On Thu, Sep 3, 2009 at 2:55 PM, Vincent Massol <vincent@massol.net> wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
Thanks -Vincent
On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
+1 Guillaume On Thu, Sep 3, 2009 at 11:35 AM, Asiri Rathnayake < asiri.rathnayake@gmail.com> wrote:
+1
On Thu, Sep 3, 2009 at 2:55 PM, Vincent Massol <vincent@massol.net> wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
Thanks -Vincent
On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
-- Guillaume Lerouge Product Manager - XWiki Skype: wikibc Twitter: glerouge http://guillaumelerouge.com/
+1 On Thu, Sep 3, 2009 at 11:25, Vincent Massol<vincent@massol.net> wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
Thanks -Vincent
On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne
+1 Thanks, Marius Vincent Massol wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
Thanks -Vincent
On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent@massol.net> wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the 2.0 release.
I'm proposing:
* 2.0RC1: 2nd of Sep * If no blocking bug found in RC1: ** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case) * If blocking bugs found in RC1: ** 2.0RC2: 9th of Sep ** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
Vincent Massol wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
+1 -- Sergiu Dumitriu http://purl.org/net/sergiu/
+1 On Thu, Sep 3, 2009 at 6:48 PM, Sergiu Dumitriu <sergiu@xwiki.com> wrote:
Vincent Massol wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the new colibri skin (lots of remaining issues), I'd like to propose to postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep * XE 2.0 final (if no RC2): 15th of Sep * XE 2.0RC2 (if blockers found in RC1): 17th of Sep * XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
+1
-- Sergiu Dumitriu http://purl.org/net/sergiu/ _______________________________________________ devs mailing list devs@xwiki.org http://lists.xwiki.org/mailman/listinfo/devs
participants (8)
-
Arvind Gupta -
Asiri Rathnayake -
Guillaume Lerouge -
Jean-Vincent Drean -
Marius Dumitru Florea -
Sergiu Dumitriu -
Thomas Mortagne -
Vincent Massol